Updated On: 11 June, 2021 07:49 AM IST | Mumbai | Vinod Kumar Menon
State housing regulator makes it mandatory for developers to certify exact Commencement Certificate stage, corresponding to progress of construction, while getting projects registered

Builders currently obtain CC for plinth level but sign sale agreements for upper floor flats that are yet to be constructed
Experts practising in RERA have lauded the state housing regulator for directing developers to submit a declaration while getting a project registered, certifying the exact stage of the Commencement Certificate. Builders often dupe buyers by obtaining project registration based on CC for just “up to a plinth or zero FSI (floor space index)”.
A circular dated June 7 (copy with this paper) by secretary MahaRERA states, “And whereas the flat buyers are unaware of this stage wise approvals, therefore, it has been decided to prescribe a declaration by the Promoter to certify the exact stage of the commencement certificate, so that flat buyers will be aware of the same.”
Ramesh Prabhu, a CA and the founder of MahaSEWA, said, “Initially, when MahaRERA started implementing RERA from 1st May 2017, it used to take only Intimation of Disapproval issued by Competent Authorities. IOD is a conditional approval given to promoters by Competent Authorities.”