Updated On: 22 March, 2024 04:57 AM IST | Mumbai | Sameer Surve
Approvals arrive for demolition and rebuilding of three small nullah crossings over SV Road, Veera Desai Road and Caesar Road, which could affect traffic for 18 months

The bridge on Veera Desai Road in Andheri on March 21. Pic/Anurag Ahire
The nightmare doesn’t seem to be ending for Andheri residents as the Brihanmumbai Municipal Corporation (BMC) has now decided to demolish and reconstruct three culvert bridges on the Mogra nullah on SV Road, Veera Desai Road and Caesar Road.
The BMC recently approved a proposal in this regard. According to it, the bridges are old, dilapidated, and resist the flow of rainwater during showers. The stormwater drains department of the civic body suggested the bridges department reconstruct these structures.