Updated On: 22 June, 2024 07:00 AM IST | Mumbai | A Correspondent
Connection from Amar Mahal in Chembur to Parel completed; it will boost water supply to Central Mumbai and help reduce leakage, theft

Civic chief Bhushan Gagrani, and BMC officials at the tunnel point
The Brihanmumbai Municipal Corporation (BMC) has completed another water tunnel stretching from Amar Mahal in Chembur to Parel via Wadala. With this addition, Mumbai now has the world’s second-largest water tunnel network, after New York, spanning 99.7 km. These tunnels help significantly reduce water leakage and theft. Additionally, a 5.25-km water tunnel from Amar Mahal to Trombay will be completed next year. According to records, New York City has a 111-km water tunnel network.
“The 9.7-km tunnel project was executed in two phases. The first phase, a 4.4 km tunnel from Amar Mahal to Pratiksha Nagar, began on October 8, 2021, and was completed on August 9, 2022. The second phase, a 5.25 km tunnel from Pratiksha Nagar to Parel started on September 1, 2022, with digging completed on Friday, June 21, 2024. Currently, 74 per cent of the project is finished and expected to be fully completed by 2026. The total project cost is R1,125 crore,” said a BMC official.